BEEAH Group: separate material recovery, fuel and power

BEEAH Group · UAE waste recovery operator

BEEAH Group’s public reporting describes several different routes in Sharjah, not one interchangeable recycling stream. Its materials recovery facility sorts recyclable fractions; its solid recovered fuel operation processes waste into alternative fuel for industrial users; and the Sharjah waste-to-energy plant converts residual waste to electricity. The company reported in April 2026 that the energy plant had processed one million tonnes cumulatively since opening in 2022 and was generating 30 MW. That is a cumulative plant input and an energy-generation figure, not recovered-material output. BEEAH also reported a planned second phase that would raise the plant’s design capacity, and a separate 2026 contract for a future integrated complex in Al Dhaid. Neither project should be read as current operating capacity. The public sources do not provide commodity grades, current saleable quantities, or uncommitted supply by facility.

The Sharjah complex has distinct recovery routes

BEEAH describes an MRF for recyclable fractions, an SRF facility supplying alternative fuel to cement and paper mills, a biomass facility producing wood chips and fuel, and a separate waste-to-energy plant. These outputs have different specifications and downstream uses; the sources do not publish a single common recovered-material total.

One million tonnes is cumulative plant input

BEEAH said in April 2026 that the Sharjah waste-to-energy plant had processed one million tonnes of waste since opening in 2022 and was generating 30 MW. This is a company-reported cumulative input milestone and power figure, not annual throughput, recycled tonnage, or a materials inventory.

Expansion announcements are not current capacity

A 2025 announcement described a planned second phase intended to increase Sharjah plant capacity. Separately, a June 2026 contract covers a future integrated waste-management complex in Al Dhaid. Those announced projects remain distinct from the existing Sharjah operating assets in the reviewed evidence.

Evidence register

Sources and claim boundaries

Waste, recycling and processing services

Official BEEAH page describes the MRF, SRF and biomass routes, including stated facility capacities. Capacity is not actual output or available inventory.

Open source ↗

Sharjah waste-to-energy plant reaches one-million-tonne milestone

Official April 9, 2026 update reports cumulative waste processed since 2022 and 30 MW generation; this is kept separate from material recovery.

Open source ↗

Al Dhaid integrated waste-management complex

Official June 29, 2026 announcement describes a contracted future project; it is not represented as an operating facility.

Open source ↗